Project GENESIS updates on Road Closures for the week of 10/22

October 18, 2018

Just a quick change to our 100 cottages construction schedule.

-We will need to close Village Parkway at the intersection with Ridgeview on Tuesday 10/23/18 and Wednesday 10/24/18.  Village Parkway will re-open on Thursday 10/25/18 pending any unforeseen issues and rock excavation.

-Ridgeview will need to be closed on Thursday 10/25/18 and Friday 10/26/18 and will reopen on Saturday 10/27, again pending any unforeseen issues or rock excavation. The limits of closure are the same as per my previous email. These closures are necessary to install new water lines.

genesis icon

Project GENESIS 10/15

October 15, 2018

Check out this week’s Project GENESIS updates!

The Business Office parking lot and Rehabilitation parking lot will be paved on Wednesday 10/17  (weather permitting)

Menno Haven Drive will be closed on Thursday for the final paving (weather permitting) 10/18

Next blasting event for the Resident Life Center will be on Wednesday 10/17 between 1-3PM

genesis icon

Mid-week Project GENESIS Updates 10/10

October 10, 2018

-There will be no blasting tomorrow but blasting will continue on Friday between 12-3PM

-The Business Office parking lot is closed this Friday & Saturday due to final paving and painting.

genesis icon

Project GENESIS Update 10/8

October 8, 2018

Here are this week’s Project GENESIS updates!

-More blasting throughout the week.

-The final paving for the Business Office, Restore and Menno Haven Drive October 19th

-Site preparation for both the Service Center and Memory Care Houses will happen this week

-No street closures anticipated this week

closed icon

Road Closure for 10/3

October 1, 2018

North Penn Hall Drive will be closed near 801-803 for utility work on Wednesday weather permitting.

closed icon

Road Closure and Project GENESIS Updates 9/24

September 24, 2018

– Menno Haven Drive will be closed Wednesday, Sept. 26 – Friday Sept. 28.

– Weather pending, paving of the business office parking lot will occur on Wednesday, Sept. 26.

– Stay tuned for updates on drilling and blasting procedures.

genesis icon

Project GENESIS Updates 9/18

September 18, 2018

– Paving of the business office parking lot will occur when weather conditions are favorable. Stay tuned for updates.

– Interior work continues inside the Rehabilitation Center.

– Weather permitting, work on the Memory Care Houses, SAGE Cottages, and Resident Life Center will continue.

– Fencing was put up around the Life Center at Brookview and the Small Houses at Chambers Pointe.

– Weather permitting, work will begin this week on the Service Center.

– We will be blasting rock at the Life Center site within the next few weeks. Stay tuned for updates.

genesis icon

Project GENESIS Updates 9/10

September 10, 2018

-Due to the weather this week the paving of the business office parking lot and the closing of Menno Haven for repaving will be pushed back. Stay tuned for updates.

-Interior work continues inside the Rehabilitation Center

-Weather permitting, the work on the Memory Care Houses, SAGE Cottages, and Resident Life Center will continue

genesis icon

Project GENESIS 9/5

September 5, 2018

Construction on the Memory Care Houses at Chambers Pointe starts on Friday 9/7 and will continue next week. Stay tuned for more updates!

genesis icon

Project GENESIS Update for 8/27

August 27, 2018

-The roadway is now open on Menno Haven Drive near Village Square.

-Underground utility work continues at the new 100’s cottage site

-Construction on the new Service Center on the Brookview Community will start on September 10th.

-Love construction? Stay up to date with our live stream videos of both the Rehabilitation Center and the Sage Cottages.