• Help Us Go Green

      Sign up to receive announcements and updates via email.

genesis icon

Pavement around the Life Center to come!

October 15, 2019

By the end of the month (October), they will be paving around the Life Center. More info to come!

genesis icon

Road Closure

October 10, 2019

Village Parkway is restricted to one lane behind the Life Center today, October 10.

genesis icon

Roadwork Update for 9/24

September 24, 2019

Brookview: Road signage will be installed this Friday 9/27/19 for the cottages and the line striping will take place on Monday 9/30/19. Please use caution when driving on ridgeview, horizon way, and windmill lane.

genesis icon

Roadwork update for 9/16

September 10, 2019

Brookview: The corner of Northgate Commons Rd. & Northfield Dr. by the new Health Care Center construction site is closed due to continued work on the gasline.

Please follow the detour signs to guide you through the stone lot behind Northgate until further notice.

genesis icon

Roadwork for week of 9/9

September 6, 2019

Roadwork at Brookview:

Contractors will begin the work on paving Ridge View in the area of the 100s on Tuesday September 10 around 11 AM.  Prep work will be done Tuesday afternoon and part of Wednesday morning.  Paving will follow.  During this time, traffic flow maybe restricted due to work being performed. The intersection of Village Parkway and Ridge View will be closed a couple hours on Tuesday and Wednesday.  Workers will assist traffic in getting through the area.  All roads will be passable in the evening – they just might be a little rough. All work should be completed by Thursday evening.

genesis icon

Project GENESIS update for 9/3

September 3, 2019

Brookview:
Paving will take place on 9/3 at Village Parkway from the Service Center entrance road to Ridge View. Please use alternate parking other than the spaces to the south of the Healthcare Center as residents will need these spots for parking.

There will be installation of fiber optics on the north side of Sunflower Drive. Please use caution driving in this area.

genesis icon

Northgate Gas Line

August 28, 2019

Brookview: On Thursday August 29 at 8:30 AM, gas service will be shut down at Northgate as a new meter gets installed to service that building. Gas is scheduled to be back on line by 3:30 PM.

genesis icon

Road Construction for August 26

August 22, 2019

On Monday, August 26 from approximately 7AM – 12PM, the intersection of Village Parkway and Honey Locust Dr. will be closed. Construction teams will be digging up the road to continue work on the gas line for the new Health Care Center.

genesis icon

Reminder on Road Closure

August 22, 2019

The section of Village Parkway that is North of Honey Locust is closed on 8/22 and 8/23 due to Project GENESIS construction.

To access the section of Village Parkway behind the Life Center, please use Honey Locust Dr.

genesis icon

Brookview Road Closures for the week of 8/20

August 20, 2019

Brookview: Traffic will be restricted on Terrace Drive today (8/20) between Scotland Avenue and Village Parkway due to the gas line project. They are trying to keep one lane open during the day.

Honey Locust will be closed this week due to the gas line.

Village Parkway will maintain open with one lane. Please use caution.